Safety note: Admin approval is an initial review, not a guarantee that every detail is correct. Check important or urgent claims with official sources and report anything inaccurate or unsafe.
Source and credit: Contributor's own report
Tasmania’s EPA Raises Concerns Over AI Data Centre’s 276 Diesel Generators - George Town, Tasmania
Smart summary
Tasmania’s environmental regulator is seeking to participate in a tribunal appeal after concerns that a proposed AI data centre could use hundreds of diesel generators more frequently than originally disclosed.
Tasmania’s environmental regulator has raised concerns about the proposed operation of a major artificial intelligence data centre in northern Tasmania, focusing on plans involving 276 on-site diesel generators. The project, proposed by Firmus Technologies, received approval from George Town Council earlier in 2026. The planned facility has a capacity of 288 megawatts and is intended to support the growing demand for computing infrastructure used by artificial intelligence systems.
The original approval included restrictions on when the diesel generators could operate. According to the regulator, the generators were initially presented as emergency equipment for power failures, with limited additional operation for scheduled testing and maintenance.
However, Firmus has appealed the restrictions through the Tasmanian Civil and Administrative Tribunal. The company argues that it should be permitted to use the generators in additional circumstances, including to supplement electricity from the main grid, manage energy security and maintain reliability when electricity markets are under pressure.
The Environment Protection Authority’s board has applied to join the tribunal proceedings. In a submission dated 7 October, the board said the expanded use described in the appeal differed significantly from what it understood when the project was initially considered.
The regulator argued that, had the broader generator-use proposal been presented from the beginning, it might have reached a different decision about whether a formal environmental assessment was required. It also warned that allowing the expanded use without appropriate assessment could create environmental risks, including noise nuisance and other potential impacts.
The dispute comes as Australia faces growing questions about the electricity and infrastructure requirements of AI data centres. These facilities require substantial power to operate computer servers and cooling systems. Diesel generators can provide backup electricity, but their more frequent use raises questions about emissions, noise and the environmental effects on surrounding communities.
The issue is particularly significant in northern Tasmania, where several data centre projects have been proposed. Residents and community groups have raised concerns about the possible effects of industrial development on local amenity and the environment.
There is also a separate question about renewable energy commitments. Firmus has previously indicated that it would support new renewable generation equivalent to twice the electricity used by its planned data centres. However, a recent company submission to a federal parliamentary inquiry stated that the associated renewable projects would not necessarily be located within Tasmania.
That distinction has attracted attention because local energy projects could affect how much new generation capacity is developed within the state. Hydro Tasmania has said the renewable projects it is considering in relation to Firmus’s power requirements are located in Tasmania.
The tribunal process will help determine whether the generator-use restrictions should remain in place. The EPA has said it will not comment further while the matter is under consideration, and Firmus declined to comment on the dispute.
TasmaniaGeneratorsDataElectricityFirmus
Tasmania’s environmental regulator has raised concerns about the proposed operation of a major artificial intelligence data centre in northern Tasmania, focusing on plans involving 276 on-site diesel generators. The project, proposed by Firmus Technologies, received approval from George Town Council earlier in 2026. The planned facility has a capacity of 288 megawatts and is intended to support the growing demand for computing infrastructure used by artificial intelligence systems.
The original approval included restrictions on when the diesel generators could operate. According to the regulator, the generators were initially presented as emergency equipment for power failures, with limited additional operation for scheduled testing and maintenance.
However, Firmus has appealed the restrictions through the Tasmanian Civil and Administrative Tribunal. The company argues that it should be permitted to use the generators in additional circumstances, including to supplement electricity from the main grid, manage energy security and maintain reliability when electricity markets are under pressure.
The Environment Protection Authority’s board has applied to join the tribunal proceedings. In a submission dated 7 October, the board said the expanded use described in the appeal differed significantly from what it understood when the project was initially considered.
The regulator argued that, had the broader generator-use proposal been presented from the beginning, it might have reached a different decision about whether a formal environmental assessment was required. It also warned that allowing the expanded use without appropriate assessment could create environmental risks, including noise nuisance and other potential impacts.
The dispute comes as Australia faces growing questions about the electricity and infrastructure requirements of AI data centres. These facilities require substantial power to operate computer servers and cooling systems. Diesel generators can provide backup electricity, but their more frequent use raises questions about emissions, noise and the environmental effects on surrounding communities.
The issue is particularly significant in northern Tasmania, where several data centre projects have been proposed. Residents and community groups have raised concerns about the possible effects of industrial development on local amenity and the environment.
There is also a separate question about renewable energy commitments. Firmus has previously indicated that it would support new renewable generation equivalent to twice the electricity used by its planned data centres. However, a recent company submission to a federal parliamentary inquiry stated that the associated renewable projects would not necessarily be located within Tasmania.
That distinction has attracted attention because local energy projects could affect how much new generation capacity is developed within the state. Hydro Tasmania has said the renewable projects it is considering in relation to Firmus’s power requirements are located in Tasmania.
The tribunal process will help determine whether the generator-use restrictions should remain in place. The EPA has said it will not comment further while the matter is under consideration, and Firmus declined to comment on the dispute.
Five artificial intelligence-powered cameras are expected to be installed across Gippsland ahead of the 2027 fire season, helping emergency services det...
New training technology at Mount Isa TAFE is giving students the opportunity to experience mining, construction and transport machinery before entering...
Concerns are growing over the reliability and availability of Australia's public electric vehicle charging network, with thousands of charging points po...
Residents have rallied against a proposed 1,200-megawatt artificial intelligence data centre near Tungkillo, raising concerns about water supplies, land...
A 52-year-old man has been arrested and charged after allegedly firing multiple shots towards two men and a 13-year-old boy who were moving cattle on a...
A new Men's Hub has opened in Kununurra to provide culturally safe healthcare and encourage Aboriginal men to attend regular medical check-ups, addressi...
A contract worker has died at Regis Resources' Duketon South mining operation in the Goldfields, prompting investigations by Work Safe and Western Austra...
Two men and a woman have been charged after an alleged disturbing incident at a funeral home in Browns Plains, south of Brisbane. Police allege a man in...
A 52-year-old man has been arrested and charged after allegedly firing multiple shots towards two men and a 13-year-old boy who were moving cattle on a...
NSW Police have appealed for public assistance after a series of alleged armed robberies involving knives, a stolen SUV and a police pursuit in the Newc...
Police have arrested three people after a suspected stolen Porsche SUV led officers on a pursuit through western Sydney. Two firearms and mobile phones...
An independent Queensland Health investigation has found that serious failures in urology services at Townsville Hospital could have been addressed year...